At the Township
What happened at the Moon Township supervisors meeting, 5 August 2026
Township approved a $500,000 park improvement grant application and a new daycare development plan.

Meeting video produced by MCA-TV, Moon Township’s public access station since 1985.
Approved
- Meeting minutes of June 24, 2026 Workshop Meeting, July 1, 2026 Regular Meeting, and July 7, 2026 Special Meeting approved.
- The seat for the three-year unexpired term of the Moon Parks Foundation was filled until the first Monday, January 2028.
- Approved Resolution R-19-2026 appointing the Township Manager as Voting Delegate/Resolutions Committee Appointment at the PML 2026 Municipal Leadership Summit on October 7-10, 2026.
- Approved appointment of Turnley Robertson & Associates Inc for auditing services for years ended December 31, 2026 through 2030.
- Approved the 2026-2027 Archery Only Deer Hunting Program.
- Approved a $500.00 donation to Hope Grows in support of their Healing Gardens.
- Approved the Major Land Development Plan for Genius Kids Daycare as recommended by the Planning Director in memo dated July 31, 2026.
- Approved the Simple Subdivision for Rolling Hills Amendment No. 10 as recommended by the Township Engineer in letter dated July 20, 2026.
- Approved Bond Reduction Request No. 5 for Wiltshire Estates, Phase from $2,750 to $0 as recommended in Township Engineer's letter dated July 29, 2026.
- Approved Bond Reduction Request No. 4 for Wiltshire Estates, Ph. 5 from $16,728.26 to $11,228.26 as recommended by Township Engineer in letter dated July 29, 2026.
- Approved Bond Reduction Request No. 9 for Wiltshire Estates, Ph. 1 from $11,000 to $0 as recommended by Township Engineer in letter dated July 29, 2026.
- Approved authorizing Township Manager to provide letter confirming $4,000 local match to support RideACTA shuttle program for FY26-27.
- Approved Change Order No. 1 for Contract 24-S01-West End Avenue Stairs not to exceed $70,000.00.
- Approved Concurring Resolution R-21-2026 authorizing filing of application for funds with Redevelopment Authority of Allegheny County (RACC) for Township Wide Park Improvements and Rehabilitation in the amount of $500,000.00.
- Approved payment of invoices: General Fund $294,951.86 (August 3, 2026); Capital Reserve Fund $90,478.60 (August 3, 2026); Stormwater Fund $63,024.13 (July 31, 2026); Sponsorship Fund $3,735.50 (July 31, 2026); Bond Fund $1,014.75 (July 31, 2026); Fire Escrow Fund $37,793.52 (July 31, 2026).
Rejected or postponed
- None.
Still open
- A complaint regarding damage from the sewer water project on Hassam Road remains unresolved. The Board discussed concerns about yard restoration, incorrectly planted trees, and unauthorized landscape beds. Township staff committed to re-addressing the landscaping, tree selection, and yard aeration in the fall, but no formal motion or decision was made on the specific requests.
SourcesWritten from the meeting agenda and a machine transcript of the recording. Names of individuals are left out; the official minutes are the record. [The agenda and minutes for this meeting](https://moontwppa.portal.civicclerk.com/) are published by the Township.